This section tells you how to create and complete a request for change and what to
do with it at each stage of the process. After following the steps you will have
implemented a basic change management process.
We have created a template request for change form that you may download and
add to, or personalise with any existing additional steps you may already have in
place - for example, additional approvers.
There is also an optional change advisory committee section which you may
choose to implement or not, depending upon what is appropriate for your school.
|
|
First select the change to which the change management process will be applied.
In FITS Change Management a change is the result of:
- a problem requiring a change for resolution and that is affecting more than one
user, such as a server hardware failure
- a new requirement as a result of advances in technology or needs, such as a
software upgrade with new functionality.
- A change may be identified by:
- a technician
- anyone responsible for ICT strategy.
|
|
A new request for change should be created for each change. You must do this
before you buy items or spend any time preparing the change, so that you can seek
appropriate approval first.
The originator should create the request for change. A request for change in this
context should not be confused with a user request for a change to their computer
or other personal ICT facilities. This is initiated using the incident/request form and
its application is described in Incident Management. The request for change form
referred to here relates to changes to shared ICT infrastructure that are initiated by
ICT staff, although these may be as a result of a user incident or request. End-
users are not required to complete change management requests for change.
We have created a request for change template which you can download and use
as it is or customise. See also example request for change. The following sections
on the request for change should be completed at this stage:
|
|
The unique identifier is a reference that applies only to the item to be changed.
This may be:
- an asset tag number
- the serial number
- any other naming or numbering system in use by the school, such as room
number and desk number.
For clarity, the unique identifier should be entered on the request for change form,
especially if the make/model/type exists more than once.
Example:
|
Unique identifier
|
Asset tag 21383
|
|
|
The name of the item to which the change applies should be entered on the request
for change form.
This may be:
- make and model of computer, printer or other equipment
- name of application and version if applicable
- assigned name of equipment, such as file server name or printer queue
name.
The purpose of this is to give a meaningful name to associate with the unique
identifier, as it is unlikely that the unique identifier alone will immediately identify the
type of equipment to the reader of the form.
Example:
|
Name of item
|
Compaq file server [server name], B Block computer room
|
|
|
A brief description of the proposed change should be entered on the request for
change.
This should include:
- nature of change
- any new equipment required
- any known costs
- estimated amount of time to plan and implement the change.
The purpose of this is to provide sufficient information to enable the initial approver
to assess the cost in time and money of carrying out the change.
Example:
|
Brief description of
change
|
Installation of Microsoft W2000 Server Service Pack 2
|
|
|
A brief description of the reason for the change should be entered on the request
for change.
This may include:
- outline of problem to be resolved by change
- justification of need for new service
- if applicable, name of the person responsible for funding or departmental
budget to be charged.
The purpose of this is to provide sufficient information to enable the initial approver
to assess the value of carrying out the change.
Example:
|
Reason for change
|
Operating system patch available to fix bugs
|
|
|
- Enter the name of the originator so that approvers know whom to talk to if they
require further information.
- Enter the name of the initial approver so that it is clear who is responsible for
this level of approval.
Example:
|
Originator
|
Andrew Powell, Network Manager
|
|
Initial approver
|
Debbie Wiggins, ICT Co-ordinator
|
|
|
|
Approval to proceed is granted (or not) by the initial approver, who must assess the
cost and value of proceeding with the change. If insufficient information is on the
request for change to enable the initial approver to make an assessment, they
should refer back for further details to the originator, who must also update the
request for change for the record.
This stage of approval is important, as it prevents time and money being wasted on
activities that may be inappropriate in terms of strategy and the bigger picture. The
initial approver (see roles and responsibilities) has the power to approve, reject or
place on hold proposed changes as they see fit and should have the appropriate
level of authority.
|
Originator
|
Andrew Powell, Network Manager
|
|
Initial approver
|
Debbie Wiggins, ICT Co-ordinator
|
D Wiggins
|
|
|
Once approval to proceed has been granted, the originator may plan and prepare
the change in earnest.
The following sections on the request for change must be completed at this stage:
|
|
Full details of the change should be entered on the request for change.
This should include:
- plan for testing/testing carried out
- plan for implementation (steps to be taken, specific requirements for
equipment and people, and so on)
- further timing details.
The purpose of this is to provide sufficient information to enable the peer reviewer
and the final approver to assess the suitability and robustness of the change and
plan before approving implementation.
Example:
|
Full details of change
|
- Check back-ups successful
- Shut down server
- Restart server
- Login as admin user
- Apply service pack from supplier
- Execute upgrade
- Restart server
- Log in to server (test functionality and review error logs)
|
|
|
Details of the impact of the change on existing ICT services and users should be
described.
This should include:
- whether or not the change will require downtime of existing services
- how long downtime will be for
- whether or not services may be disrupted during implementation of the
change
- what services will be affected by downtime or disruption
- which users are affected
- whether or not timing of change reduces impact.
The purpose of this is to highlight the disruption to normal day-to-day activities that
are likely to occur during implementation of the change and to enable the final
approver to assess whether or not the disruption is acceptable.
Example:
|
Impact on services
and users
|
- Server unavailable for one hour
- Users unable to log in to computers for duration
- ICT services unavailable for duration
- Affects all users and services
|
|
|
Details of the impact and risk of failure of the change should be outlined.
This should include:
- whether a failure of the change may result in an unplanned outage
- what services would be affected by an unplanned outage
- which users would be affected by an unplanned outage
- what the risk of failure is estimated to be (high risk or low risk)
- what has been done to reduce the risk (for instance, any testing that has
been carried out)
- what risk mitigation has been carried out (such as a dry run of the
installation using test equipment).
The purpose of this is to highlight the risks associated with the change if
implementation does not go according to plan and to highlight the potential
disruption to normal day-to- day activities.
Example:
|
Impact and risk of
change failure
|
- Failure would require server rebuild and data restore
- Estimated time to rebuild, restore and recover: 6 hours
- Impact on services and users as above
- Risk low – service pack released two months ago and no
issues reported on the supplier’s website
|
|
|
Details of a fallback plan for implementation in the event of change failure should be
outlined.
This should include:
- what needs to be done to restore the service to its original state before
the change was attempted
- what equipment or other resources are needed to be available to
implement the fallback plan
- confirmation that equipment or resources have been arranged
- at what point the fallback plan will be invoked - for example, if work
overruns and an unplanned outage is unacceptable.
The purpose of this is to demonstrate that a plan is in place for service recovery in
the event of change failure. If a change fails, it is important that all original
components are restored so that inventory records remain accurate. See
Configuration Management for further details.
Example:
|
Fallback plan
|
- Restore operating system and data from tape
- Restart server
- Test server and data
NB Tapes required on site in advance of change
|
|
|
The date and time that the change will be implemented should be recorded on the
request for change.
An estimate of the amount of time the change will take should also be included.
Example:
|
Date of change
|
Friday 25 April 2003
|
|
Time of change
|
1800 – 1900
|
|
|
- Enter the name of the peer reviewer so that it is clear who is responsible
for this
level of approval.
- Enter the name of the implementer so that it is clear who will/did carry out the
change.
- Enter the name of the final approver so that it is clear who is responsible for this
level of approval.
Example:
|
Originator
|
Andrew Powell, Network Manager
|
|
Initial approver
|
Debbie Wiggins, ICT Co-ordinator
|
D Wiggins
|
|
Peer reviewer
|
James Burke, Supplier
Representative
|
|
|
Final approver
|
Debbie Wiggins (for Headteacher)
|
|
|
|
|
Success
|
Failure
|
|
Implementer
|
Andrew Powell, Network Manager
|
|
|
|
|
On completion of the request for change, approval to implement is recommended
(or not) from a technical perspective by the peer reviewer, who must assess the
change and implementation plan for technical suitability and robustness of
solution. If insufficient information is on the request for change to enable the peer
reviewer to make an assessment, they should refer back for further details to the
originator, who must also update the request for change for the record.
|
Originator
|
Andrew Powell, Network Manager
|
|
Initial approver
|
Debbie Wiggins, ICT Co-ordinator
|
D Wiggins
|
|
Peer reviewer
|
James Burke, Supplier
Representative
|
J Burke
|
|
Final approver
|
Debbie Wiggins (for Headteacher)
|
|
|
|
|
Success
|
Failure
|
|
Implementer
|
Andrew Powell, Network Manager
|
|
|
|
|
Following approval by the peer reviewer, ultimate approval to implement is granted
(or not) by the final approver. They should seek the views of affected or relevant
user representatives to take part in this decision- making process. If insufficient
information is on the request for change to enable the final approver to make an
assessment they should refer back for further details to the originator, who must
also update the request for change for the record.
|
Originator
|
Andrew Powell, Network Manager
|
|
Initial approver
|
Debbie Wiggins, ICT Co-ordinator
|
D Wiggins
|
|
Peer reviewer
|
James Burke, Supplier
Representative
|
J Burke
|
|
Final approver
|
Debbie Wiggins (for Headteacher)
|
D Wiggins
|
|
|
|
Success
|
Failure
|
|
Implementer
|
Andrew Powell, Network Manager
|
|
|
|
|
It is important to communicate relevant details of the change to affected users. It is
not necessary to distribute full technical details of the change, but those dependent
upon the ICT services affected will appreciate a brief outline of the user impact.
A change communication should include:
- a simple description of the change, for instance installation of anti- virus
software
- date and time of change
- services affected
- users affected
- nature of impact, such as complete outage
- duration of impact
- contact name and details for further information.
It is good practice to present such changes in a positive light by highlighting the
benefits of the change.
See the toolkit for an example of change communication.
It is also good practice to have a standard method for communication so that users
can come to expect a similar format for everything related to ICT. It may be a good
idea to make one person responsible for all communications. A consistent forum is
also a good idea, for example, staff briefing meetings or intranet home page.
|
|
Following final approval and after relevant and timely communications have been
issued, the change may be implemented in accordance with the plan and the
scheduled date and time.
It should be recorded on the request for change whether the change was successful
or unsuccessful, so that it is clear from the record what the outcome of the request
for change was.
|
Originator
|
Andrew Powell, Network Manager
|
|
Initial approver
|
Debbie Wiggins, ICT Co-ordinator
|
D Wiggins
|
|
Peer reviewer
|
James Burke, Supplier
Representative
|
J Burke
|
|
Final approver
|
Debbie Wiggins (for Headteacher)
|
D Wiggins
|
|
|
|
Success
|
Failure
|
|
Implementer
|
Andrew Powell, Network Manager
|
X
|
|
|
|
Following successful change, inventory records should be updated to reflect the
details. For example, if a file server is replaced and the old one is disposed of, the
new file server needs to be recorded on the inventory with details such as make,
model, serial number, asset tag number. Details of the old one must be removed.
The following are some examples of outcomes that may require inventory update:
- installing new hardware
- removing hardware
- installing new software
- reassigning a software licence to another user.
This activity forms part of the Configuration Management process, which is the
subject of a separate section of FITS.
|
|
Congratulations, you have completed your request for change!
You should retain the signed paperwork for future reference.
|
|
A change advisory committee may be set up as a forum for the review and
approval or rejection of proposed changes and change plans.
Membership of the change advisory committee should include but is not restricted
to:
- Change manager, for example ICT manager or person responsible for ICT or
technical support
- ICT technical representative, for example ICT manager or senior technical
person
- strategic representative, for example headteacher
- user representative(s), for example ICT co-ordinator, teacher(s)
- other ad hoc representatives for specific changes as required.
Consensus may be achieved via a brief meeting that may be either scheduled to
take place regularly or arranged as required. These should be treated as formal
meetings
The change advisory committee is in addition to the request for change process
and should be used only if it enhances the process. It may be helpful to have a
regular meeting at which all changes are discussed and approved. But, depending
upon the volume and frequency of changes, this may get in the way of change -
which is not an acceptable feature of the process!
You may find it safer to consider each change as it arises, at least until the process
is familiar, to avoid wasting time in unnecessary meetings and to avoid delaying
changes. This also makes it easier to review emergency changes if all changes
are dealt with as they arise.
|
|
The change advisory committee meeting should approve or reject changes. The
change manager should manage the meeting and facilitate agreement.
Creative use of technology can be used in place of a physical meeting. For
example, you could to circulate requests for change and gather responses by
email, or hold a virtual meeting via telephone conferencing. The latter methods can
be particularly useful for gaining agreement in emergencies without taking up too
much time and without having to wait for a meeting.
|
Agenda
|
A day or so before the meeting send out an agenda including hard
copies of, or electronic links to, the requests for change to be
discussed.
The membership should be asked to review all requests for
change in advance of the meeting and be prepared with any
questions or concerns. This ensures that the meeting is kept
precisely for the purpose of approval or rejection and does not
become a lengthy explanation of each change. If the details on a
request for change are not self-explanatory, the request should be
rejected before circulation.
An example agenda can be found in the toolkit.
|
|
Minutes
|
A brief record of the outcome of change advisory committee
meetings should be circulated for acceptance and kept for the
record. These minutes should include approvals and rejections
and any action points, those responsible for taking the actions and
deadlines.
Example minutes can be found in the toolkit.
|
|
|
|
|
|